Sprint: Merrimac, WI

Client Name
Sprint
Project Location
Merrimac, WI
Completion Date
February 2019
Solutions Provided
HDD, Collaborative Delivery, Project Management
Scope

In the winter of 2018–2019, Gabe’s HDD crew drilled 2,970 feet under Lake Wisconsin. Their team needed to install a 6” steel pipe, from pilot to pull, in the jettable soils underneath the lake — all in harsh winter conditions. Their civil crew also removed fiber from an existing rail bridge using a high-rail snooper truck.

Challenges

Their team had minimal, narrow, workspace in the railroad’s right-of-way, which required extensive planning to navigate. They also had to carefully remove and relocate existing fiber lines. Finally, Gabe’s needed a clever solution for running surface steering wire on and under variable ice flows and open water. Inspired by Wisconsin ice fishermen, they ran the wire with an airboat — a quick solve that got the job done.

Our Impact

2.9K+

Feet of Steel Pipe